CSAH 3 Bridge Reconstruction and Pavement Preservation Project
Project description: Olmsted County is leading a project to reconstruct the County State Aid Highway (CSAH) 3 Bridge south of Pine Island and complete pavement preservation from 8th St SW in south to the CSAH 5 roundabout.
Project location map:
Anticipated project schedule:
Project description: Olmsted County is leading a project to reconstruct the bridge over the Middle Fork Zumbro River and 0.25 Miles of roadway south of 8th St SW in Pine Island. The project will also recondition 0.35 miles of pavement south of the bridge to the County 5 Roundabout. The bridge is anticipated to be closed for the duration of the project.
Contractor: Minnowa Construction Inc.
Anticipated Project schedule:
Starting - May 15, 2026
Completion - August 27, 2026
Public Works contact: Assistant County Engineer, Nathan Arnold 507-328-7060 | nathan.arnold@olmstedcounty.gov