Soil Boring Work on County State Aid Highways (CSAH) 5 and 25 beginning December 14, 2022
Olmsted County Public Works will be performing soil boring work beginning Wednesday, December 14, 2022. The work will be performed on CSAH 5 from Trunk Highway (TH) 14 to CSAH 25, and on CSAH 25 from CSAH 5 to CSAH 3 as shown on the map below. Traffic will be reduced to a single lane with flaggers directing traffic. The work is in preparation for a future roadway reconstruction project. Braun Intertec is the contractor completing the work. The soil boring work is estimated to be complete on December 23, 2022, weather permitting.
![5 & 25 Detour](/sites/default/files/styles/standard/public/2022-12/5%2625.png.webp?itok=yZUtfd6w)
Reminder
Motorists are reminded to always drive with caution, and never enter a road blocked with barriers or cones. Please reduce your speed and proceed with caution through these work zones.
Access the Road Closure Map Here
Media Contact: Sue Struckmann | sue.struckmann@olmstedcounty.gov | 507-328-7070